Se San 4A Hydropower plant, Gia Lai province, was constructed in IAO commune, IAGRAI district - Gia Lai province. It has installed capacity of 63 MW, with 3 generator units and total investment budget of 1.559 billion VND. After the machine unit 3 is put into operation, it will supply about 331 million KWh/year to the national grid.
Machinery and Industrial Equipment Corporation is the leader of joint venture of MIE - LILAMA 45.3 - BACH KHOA JSC to supply hydraulic mechanical equipment.
- Commencement: November, 2008
- Generator unit 1 was connected to the national grid on July 15th, 2011.
- Generator unit 2 was connected to the national grid on September 4th, 2011.
- Generator unit 3 was connected to the national grid on November 3rd, 2011.
ORTHER NEWS
- › Bao Lam 3 Hydropower Project (15/07/2018)
- › Bao Lam 3A Hydropower project (05/07/2018)
- › Lai Chau Hydropower Project (02/06/2017)
- › Pa Chien hydropower project (02/06/2017)
- › Expansion of sulfuric acid production lines for Tan Binh chemical factory (02/06/2017)
- › Na Tau Hydropower Plant (02/06/2017)
- › Project of Tanks for H2O2 - 500 m3 - Hung Pha Ha Bac JSC (02/06/2017)
- › Supply and installation for OПB10 -145 circulation pump - Pha Lai Thermoelectric Joint Stock Company (02/06/2017)
- › Project of Upgrading for DCS system - Ha Bac Fertilizer Co.,ltd (02/06/2017)
- › Hong Phong Cement Plant - Lang Son Province (02/06/2017)
- › Manufacture of pipeline system hfo pipe supporting rack for project of Pha Lai 2 thermoelectric plant (02/06/2017)
- › Cao Ngan thermoelectric plant - Thai Nguyen (02/06/2017)
- › Manufacture supply of equipment for project of Ba Ria 2 steam stern plant (02/06/2017)
- › Manufacture assembly of equipment for casting line of 6000 ton year (02/06/2017)
- › Supply of equipment for Lam Son sugar factory- Thanh Hoa (02/06/2017)